Fall 2025 Update: Silencer installed at Hants Border Wastewater Treatment Plant

The new equipment ordered to address odour and noise at the Hants Border Wastewater Treatment Plant is now in place.

The action taken to combat odour in the spring and summer of 2025 greatly reduced the odour, but new concerns arose about the noise from the blower equipment used to address the smell.

A new, custom-ordered silencer was delivered in September, and crews worked fast to get it installed by Sept. 17.

The Municipality of the County of Kings thanks community members for their patience and understanding as staff worked to address the odour and noise.

Future updates about the Hants Border Wastewater Treatment Plant will be shared on this new webpage.

Hants Border Sewer
Progress Reports
09-29-2025 Hants Border Silencer Installed.pdf (265 KB)
09-16-2025 Hants Border Wastewater Silencer Install.pdf (252 KB)
09-09-2025 Hants Border Letter.pdf (116 KB)
05-23-2025 Hants Border Odour.pdf (150 KB)